Article

Force majeure clauses and supply chain disruption

30th March 2022

Many companies are currently facing disruption to their supply chains and suppliers are often relying on force majeure (FM) clauses to suspend their obligations under a supply agreement.

Last week I advised a multi-billion-pound turnover engineering business on a supply contract in which the supplier was seeking to rely on the war in Ukraine as a FM event. It turned out that the much bigger issue was which party’s terms applied, commonly known as ‘a battle of the forms’. Whilst this is not a perfect example of an FM debate running its course, it demonstrates the fact that even the largest companies are experiencing supply chain issues with little or no immediate legal remedy.

More broadly, FM clauses have been brought into the spotlight during the pandemic with suppliers and customers seeking to rely on ‘epidemic’ and ‘pandemic’ as trigger events. Pandemic aside, the importance of FM clauses in the supply chain cannot be underestimated, as demonstrated by the example above and the Suez Canal incident in March 2021.

What is FM?

FM clauses are designed to cover scenarios in which one or both parties are unable to perform their obligations under a contract because of events beyond their reasonable control. These clauses tend to suspend the obligations of the party relying on the FM event and, depending on the drafting, may lead to the contract being terminated.

Drafting and interpretation of FM clauses

It is important to note that FM clauses must be carefully drafted. Under English law, there is no doctrine of FM, nor any statutory definition for it. The term has its origins in French civil law and can be translated as ‘superior force’.

FM clauses are therefore interpreted under common law. This means that parties have the flexibility to set the context as they want to within the contract.

If a dispute was to arise over the interpretation of an FM clause, this would probably be decided with reference to case law. The importance of drafting was emphasised by the case of Tandrin Aviation Holdings Ltd v Aero Toy Store LLC and others [2010] EWHC 40. The judgment in this case cautioned against relying on catch-all wording in FM clauses.

In this case, there was a clause listing specific events, followed by a catch-all provision which covered any other events beyond Aero Toy Store’s (ATS) reasonable control. ATS sought to rely on the catch-all provision to say that the 2008 financial crisis was an event beyond its reasonable control – triggering the FM event.

However, the court held that the FM clause did not cover the financial crisis. This was because neither ‘economic downturn’ nor any similar wording was included in the list of events to which the clause would apply. However, creating a list of FM trigger events should be given careful consideration; a broader list can help future-proof the contract, but casting the net too wide can also dilute a party’s commitment to supply or pay for the goods or service.

Acts of war

The war in Ukraine has caused disruption to supply chains across Europe and further afield. The closure of ports, imposition of sanctions and a no-fly zone have meant both suppliers and customers have felt an immediate impact.

Most FM clauses will include reference to acts of war as a trigger event and parties have been seeking to rely on such clauses to suspend or terminate contracts.

What should I do as a supplier and as a customer?

In the first instance, we recommend parties seeking to rely on such clauses take steps to review their rights and remedies under the wider agreement. For example, a ‘termination for convenience’ clause – which allows for termination of a contract without reason – or a ‘termination for material breach’ clause – which allows for termination of contracts due to serious breaches – may provide for an effective and immediate remedy.

Most FM clauses include a period in which the party relying on the event can suspend their obligations before the other party can then terminate. Typically, I see contracts with FM clauses providing for a 90-day suspension.

If a party seeks to rely on an FM clause as its primary remedy, it may choose to rely on acts of war as a trigger event. The case of Classic Maritime Inc. v Limbungan Makmur [2019] EWCA Civ 1102, states that reliance on acts of war require that the war materially affects performance of the contract rather than completely preventing performance.

The difficulty comes when you have, for example, a prominent and established English football club, Chelsea FC (CFC), which is wholly owned by a Russian billionaire whose assets have been frozen. Can CFC rely on acts of war as an FM event, and so suspend their obligations under a variety of supply contracts?

Very simply, we do not know until these clauses are tested in the courts.

What we do know is that there is an indication that acts of war clauses will be revisited in further detail and may warrant a separate clause dealing with the same.

Before exercising an FM clause in this context, we recommend you should:

  • Check the governing law and jurisdiction clauses of the contract – if the agreement is governed by the laws of another country, you should seek advice from a local lawyer before enforcing the clause
  • Seek or provide clarity – as a customer you will want to know the reasons why a supplier is unable to fulfil their order
  • Ask if there is an alternative way of performing – review the situation and ask the supplier to fulfil the order through alternative means. For example, your supplier may have an alternative location in another country
  • Consider the humanitarian tragedy – the customers and/or suppliers you are dealing with may have family members in the war. It is imperative that you provide adequate time for a response before escalating
  • Seek legal advice on an FM clause before seeking to exercise it.

Conclusion

The importance of FM clauses is of increasing importance. Whether parties seek to rely on a pandemic, act of war or another FM event, the days of thinking that these clauses are simply boiler plates are well and truly over.

Related Blogs

View All